Standard Service Last Resort Service RFPs

Standard Service & Last Resort Service RFPs

2025 Standard Service and Last Resort Service RFP

Bid Day is s Wednesday April 16, 2025 - All Bids are due to UI at 10 AM EPT

April 16, 2025 is the next Standard Service and Last Resort Service RFP for up to 20% of 2nd Half of 2025 Load and up to 40% of 1st Half of 2026 Load for Standard Service and 3nd Quarter 2025 LRS load.

Mapping of GST and LPT Load for January 22, 2025 Bid Day

For the one-year period that ended September 30, 2024 the following mapping represents actual mapping of GST and LPT load: For GST, 68.9% was mapped to Standard Service eligibility for energy (kWh) and 68.0% for demand (kW).  For LPT, 27.8% was mapped to Standard Service eligibility for energy (kWh) and 27.8% for demand (kW).  For GST, 31.1% was mapped to Last Resort Service eligibility for energy (kWh) and 32.0% for demand (kW). For LPT, 72.2% was mapped to Last Resort Service eligibility for energy and 72.2% for demand (kW).

Visit the pages below for RFP information

SS & LRS RFP Documents

SS LRS Bid Day Schedule for January 22, 2025 Bid Day

 

Item

Date

RFP Issued

Thursday, December 19, 2024

Bidder Information Forms Due (Forms available on UI Wholesale Power Procurement website) Thursday, January 2, 2025: 4:00PM
New Bidder Comments on Master WPSA Due Friday, January 3, 2025: 4:00PM
New Bidder Master WPSA Discussions / Negotiations Monday, January 13, 2025 through Friday, January 17, 2025
Last Questions / Inquiries for Q&A Thursday, January 16, 2025: 4:00PM
New Bidder Master WPSA Fully Executed Thursday, January 16, 2025: 4:00PM
Bid Assurance Due Thursday, January 16, 2025: 4:00PM
Final Binding Bids Due Wednesday, January 22, 2025: 10:00AM
Expected Notification of Winning Bidder(s) Wednesday, January 22, 2025: By 1:00PM
Executed Confirmations and Guarantees Due via email or FAX Thursday, January 23, 2025: Close of Business
Original Guarantees Due Monday, January 27, 2025: Close of Business